O3b Asks for More Time for Meeting MPower Milestones
SES' O3b is asking the FCC for 26 additional months to meet milestones for making operational its Ka-band satellites authorized in the agency's U.S. market access order. In an FCC Space Bureau application posted Monday, O3b said the COVID-19 pandemic…
Sign up for a free preview to unlock the rest of this article
Communications Daily is required reading for senior executives at top telecom corporations, law firms, lobbying organizations, associations and government agencies (including the FCC). Join them today!
initially delayed its mPower satellites. Next, performance deficiencies were discovered in 2023 in the first four mPowers. It said design updates addressing those issues delayed manufacture of later mPowers. It asked that its milestone deadline for having 50% of the mPowers in the U.S. market access application be operational move from June 7, 2024, to Aug. 7, 2026. It also asked that the milestone deadline for the remaining 50% be moved from June 7, 2027, to Aug. 7, 2029.